Electricity transmission network now easier to access after Centre notifies new rules

Centre notifies new rules providing easier access to electricity transmission network
Photo Credit :

New Delhi: Power Ministry has promulgated the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021. This paves the way for overhauling of transmission system planning, towards giving power sector utilities easier access to the electricity transmission network across the country.

At present, generating companies apply for long-term access (LTA) based on their supply tie-ups, while medium-term and short-term transmission access is acquired within the available margins. Based on LTA application, incremental transmission capacity is added. A number of sector developments, such as the increasing focus on renewable energy, and the development of the market mechanism, necessitated a review of the existing transmission planning framework based on LTA.

The rules underpin a system of transmission access which is termed as a General Network Access (GNA) in the inter-state transmission system. This provides flexibility to the States as well as the generating stations to acquire, hold and transfer transmission capacity as per their requirements.

In a major change from the present system of taking transmission access, power plants will not have to specify their target beneficiaries. The rules will also empower state power distribution and transmission companies to determine their transmission requirements and build them. Also, states will be able to purchase electricity from short term and medium-term contracts and optimise their power purchase costs.

Apart from introducing GNA, the rules also specify the clear roles of various agencies involved in the transmission planning process. The Central Electricity Authority shall prepare a short-term plan every year on a rolling basis for the next 5 years and a prospective plan every alternate year on a rolling basis for the next 10 years. The Central Transmission Utility shall prepare an implementation plan for inter-State transmission system every year on a rolling basis for up to the next 5 years which will take into account aspects such as right-of-way and progress of the generation and demand in various parts of the country.

The existing LTA would be transitioned into General Network Access as per the rules. The rules also outline the recovery of GNA charges from the users of the transmission network. They assign the responsibility of billing, collection and disbursement of charges to the Central Transmission Utility.

The rules have enabled, for the first time, that the transmission capacity can be sold, shared or purchased by the States and generators. The rules prescribe that excess drawal or injection over the GNA capacity sanctioned shall be charged at rates that are at least 25 per cent higher and this will ensure that the entities do not under-declare their GNA capacity. The Central Electricity Regulatory Commission (CERC) has been empowered to bring out detailed regulations on GNA in interstate transmission systems.

The Central government has notified these rules with a view to streamlining the process of planning, development and recovery of investment in the transmission system. The rules are aimed at encouraging investments in the generation and transmission sectors. The rules will enable the country to develop deeper markets.

The transmission system is the vital linkage in the power sector value chain connecting the generation and the demand. The Central government is committed to ensuring the adequacy of the transmission system for the supply of power from one State to another State and across regions. The rules brought out by the Central government underpin that “electricity transmission planning shall be made in such way that the lack of availability of the transmission system does not act as a brake on the growth of different regions and the transmission system shall, as far as possible, to be planned and developed matching with the growth of generation and load and while doing the planning, care shall be taken that there is no wasteful investment”.

In a series of other reforms carried out earlier, the Ministry had separated the Central Transmission Utility from POWERGRID to provide transparency and a level playing field in the bids for transmission and reduced the lock-in period for transmission projects in order to attract investments and more competition. The Ministry of Power also issued the Right of Consumer rules, which empower consumers and rules laying down the ceiling for late payment surcharges.

Share this:
MANY DROPS MAKE AN OCEAN
Support NewsKarnataka's quality independent journalism with a small contribution.

How useful was this post?

Click on a star to rate it!

Average rating 0 / 5. Vote count: 0

No votes so far! Be the first to rate this post.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Nktv
Nktv Live

To get the latest news on WhatsApp