Mysuru: District in-charge Minister Dr. Yathindra Siddaramaiah has directed Mysuru Development Authority (MDA) officials to complete the long-pending Dr. B.R. Ambedkar Bhavan by January or February 2027, stressing that construction quality must not be compromised.
The Minister issued the direction during an inspection of the under-construction Ambedkar Bhavan near Lokayukta Office Junction on Dewan’s Road on Saturday evening. He visited the site and reviewed the ongoing interior works after hearing concerns raised by Dalit leaders over the prolonged delay and alleged deficiencies in construction quality.
Dr. Yathindra said the project had remained incomplete for nearly 14 years despite being launched with the objective of providing a major facility in the heart of Mysuru. He noted that allegations regarding poor construction quality had also been raised and directed officials to arrange an independent assessment of the building.
Independent quality assessment ordered
The Minister instructed the MDA to appoint a third-party agency to inspect the construction and submit a report on the quality of the work. He emphasised that the project should not be rushed to meet a deadline at the cost of structural standards or workmanship.
“The Ambedkar Bhavan being built in the heart of Mysuru is a prestigious project. It is being constructed at a cost of about Rs. 47 crore and should be completed at the earliest without compromising on quality,” he said.
Dr. Yathindra pointed out that he had inspected the site twice since taking charge as District Minister. Officials had earlier been instructed to complete the project by the end of December 2026. However, during the latest review, they indicated that meeting the deadline would be difficult.
Taking note of the revised timeline, he asked the officials to ensure that the remaining work was completed by January or February 2027. He also stressed the need for regular monitoring so that the project would not face any further setbacks.
Contractor assures completion by February
MDA Commissioner Islauddin Gadyal informed the Minister that the quality of construction would be reviewed and that the contractor had assured completion of the project by February 2027.
The Minister asked the authority to closely supervise the remaining work and ensure that the contractor adhered to the revised schedule. He also made it clear that officials should take responsibility for monitoring progress and addressing any issues that could cause further delays.
The proposed Ambedkar Bhavan is a significant public project, particularly for the Dalit community, and its prolonged delay has been a matter of concern among community representatives. The latest inspection followed demands for the authorities to expedite the work while ensuring that the building meets the required standards.
Former Mayor compares project with Viveka Smaraka
Former Mysuru Mayor Purushotham expressed concern over the unusually long time taken to complete Ambedkar Bhavan. He pointed out that the adjacent Swami Vivekananda Memorial, known as Viveka Smaraka, had been completed within two years, whereas the Ambedkar Bhavan project remained unfinished even after 14 years.
The comparison highlighted the frustration among those seeking the completion of the facility. Dalit leaders who met the Minister during the inspection raised concerns over the delay and the need to ensure that the construction was of acceptable quality.
The Minister’s direction for an independent assessment is expected to provide an evaluation of the construction and help address the concerns raised by community representatives.
Officials and Dalit leaders attend inspection
MLC Dr. D. Thimmaiah, Mysuru City Corporation Commissioner M.K. Savitha, and Dalit leaders Ananthaswamy, Bettaiah Kote and Alagudu Shivakumar were present during the inspection. Advocate Puneeth and Gandhinagar Kiran Kumar also attended.
With the contractor indicating February 2027 as the completion target, the MDA will have to closely monitor the remaining work and ensure that the independent quality assessment is carried out. The Minister has made it clear that the Rs. 47-crore project must be completed without further delay and without compromising on construction standards.