Key upgrades to the Bengaluru-Ballari highway, including the Hiriyur-Challakere and Hospet-Ballari stretches, are set to improve connectivity and spur regional growth.
Highlights
- Hiriyur-Challakere Stretch:
- Sanctioned in 2018 with a budget of ₹1,167.52 crore.
- 43.8 km completed, full stretch (55.7 km) expected by April 30, 2025.
- Current expenditure: ₹890.75 crore.
- Hospet-Ballari Stretch:
- Sanctioned at ₹1,340.15 crore in December 2022.
- 61.99 km of 95.37 km completed, estimated finish by May 14, 2025.
- Expenditure so far: ₹171.97 crore.
Impact on Development
- Enhanced connectivity to regions like Kalaburgi, Lingasugur, and Andhra Pradesh.
- Real estate growth in Nelamangala and North Bengaluru driven by proximity to the upgraded highway.
- Boost in demand for housing and commercial spaces, making the area attractive for investments.
Improved road infrastructure is paving the way for economic growth and new opportunities in Karnataka’s key regions.