Bengaluru: Building a house in Bengaluru has become significantly more expensive this year, with construction costs rising between 10% and 25% amid supply disruptions and escalating material prices linked to the West Asia conflict, industry insiders said.
Developers, architects and contractors say the price increases have affected a wide range of construction materials, including steel, M-sand, boulders, paints and sanitaryware. While some supplies have gradually improved, the cost of several materials remains elevated, putting pressure on homeowners and small-scale contractors.
The rising expenses have forced some individual homeowners to reconsider their construction budgets, while several smaller residential projects have been temporarily suspended. Contractors who agreed to execute projects at previously negotiated rates are also struggling to absorb the additional expenses.
Construction costs climb to Rs 2,300–Rs 3,000 per square foot
Khalid Rehman, senior architect at the Centre for Vernacular Architecture in Bengaluru, said the cost of constructing a house has increased by nearly 25% compared with last year.
Construction costs, which previously ranged between Rs 1,800 and Rs 2,200 per square foot, have now climbed to approximately Rs 2,300–Rs 3,000 per square foot, depending on the specifications and materials used.
Several construction inputs have registered substantial price increases over the past year. M-sand, boulders, paints and sanitaryware have become considerably more expensive, with prices of some items rising by 10% to 20%. Steel and cement prices, however, have remained relatively stable compared with other materials, Rehman said.
The increase has made construction more difficult for families planning to build independent houses, particularly those who prepared budgets based on last year’s prices.
West Asia conflict disrupts material supplies
The ongoing conflict in West Asia has contributed to higher construction costs by disrupting supply chains and increasing the expenses associated with oil, gas, transportation and manufacturing.
Crude oil and gas are important inputs in the production and transportation of several construction materials. Products such as paints, plastics, PVC pipes, waterproofing materials and other industrial components are particularly exposed to fluctuations in energy and transportation costs.
Supply disruptions have also affected the availability and pricing of certain imported materials and products dependent on global logistics.
Sriram K from the Confederation of Real Estate Developers’ Associations of India (CREDAI) said supplies had improved considerably and were gradually returning to normal, but challenges remained.
He said the prices of some construction items had increased by as much as 35%, while overall construction costs had risen by at least 10%.
Although supply conditions have shown signs of improvement, industry players say the price increases have not been fully reversed, leaving builders and homeowners facing higher expenses.
Small contractors and homeowners bear the brunt
The cost escalation has disproportionately affected smaller developers and individual contractors, who generally have limited financial reserves to absorb sudden increases in material prices.
Srinivas K, a Bengaluru-based contractor, said smaller contractors who had agreed to execute projects at fixed prices were struggling to continue work because of the steep increase in construction expenses.
While larger builders may have financial resources and procurement arrangements to manage price fluctuations, smaller contractors face difficulties in maintaining their commitments.
The situation has also created disagreements between contractors and homeowners. Homeowners who entered into construction agreements based on earlier estimates are often surprised when contractors seek additional payments to cover the rising costs.
Contractors, meanwhile, say they cannot absorb the entire difference without affecting their financial viability.
The resulting disputes have complicated the execution of several residential projects, particularly those involving individual house owners and smaller developers.
Residential projects put on hold
The rising costs have led to construction delays and temporary suspensions of several projects across Bengaluru.
Partha V, another contractor, said many individual homeowners had temporarily stopped construction after their budgets increased substantially beyond the initial estimates.
He said some projects had been halted even after reaching nearly 50% completion because owners were unable to manage the additional expenses.
Contractors also said they were not in a position to absorb the cost differences, particularly when agreements had been finalised before the recent price increases.
While larger real estate projects continue to progress, several are reportedly moving slowly as developers reassess budgets, procurement plans and construction schedules.
Industry insiders expect some projects to face delays of at least a year as contractors and developers attempt to manage the financial impact of rising material costs.
Builders seek project completion extensions
The Builders’ Association of India has reportedly written to the Real Estate Regulatory Authority (RERA), seeking extensions for completing projects amid the escalating construction costs and supply-related challenges.
The request comes as builders face difficulties in adhering to timelines agreed upon before the latest cost increases.
Industry representatives say the price escalation has affected construction budgets, project execution and financial planning, particularly for projects that depend on fixed contractual rates.
With material prices remaining elevated and uncertainty surrounding supply chains, the construction industry is seeking regulatory support to prevent further delays and financial strain.
The rising cost of building houses in Bengaluru is now creating challenges for homeowners, contractors and developers alike, with smaller projects particularly vulnerable to budget overruns and interruptions.
Construction material price comparison in Bengaluru
| Material | 2025 prices | Current prices |
|---|---|---|
| Overall construction cost | Rs 1,800–Rs 2,200 per sq ft | Rs 2,300–Rs 3,000 per sq ft |
| Steel | Rs 48–Rs 55 per kg | Rs 51–Rs 90 per kg |
| Cement | Rs 280–Rs 425 per 50 kg bag | Rs 315–Rs 450 per 50 kg bag |
| M-sand | Rs 800–Rs 1,500 per tonne | Rs 1,100–Rs 1,850 per tonne |